Skip to content

Mowat Construction 2013

photo (5)

Mowat Construction was awarded a 30 million dollar contract to install the high rise columns for the 520 project in Seattle. Mowat called on Northwest to provide placing equipment on this very environmental conscience project.  Northwest has leased a Putzmeister 2110 along with a 38 meter placing boom to place the seven thousand yards in this project. All pours are being done off the existing bridge in the hours of 10 pm to 3 am as not to disrupt traffic on the very heavy burdened bridge.